The Commission on Audit has flagged around P327 million worth of Bulacan flood control projects that are either non-existent, or built but not in the approved locations.

These findings were stated in the COA Fraud Audit report on Bulacan flood control projects.

Riverwall

State auditors said that a riverwall meant for in Barangay Pagala, Sta. 00+910 to Sta. 01+310, Baliuag, Bulacan was built somewhere else.

“During COA’s inspection last September 23, 2025 no flood control project was seen at the approved location,” COA said, calling it a flood control structure which drastically falls short of the approved plan and did not have the critical supporting documents for va

📰